Repair Cracks in Front Loader Bucket

This project was off Eight Mile Road in Stockton.  Mark from Blue Iron, Inc., www.blueironinc.com, called and asked that I repair the cracks, there were several.

This was a crack around the lift pin boss

 I used an air arc, or arc gouging process to clean out the crack.  Sometimes the crack does not go all the way through the material and it is imperitive the crack is removed from the material or gouged out then welded up completely. 

Same crack repaired.

Some welders like to use the Stick welding process , SMAW, to weld these cracks up typically a rod with the 7018 designation.  This process is adequite, it provides a strong weld and when done properly the crack should not come back.  However it has one down fall and in my opinion only one, its speed.  I was able to utilize the wire welding process, FCAW, I used NR 232. 

Anothercrack in the same bucket

Crack welded up

Another view of cracks welded up.

There were a total of 12 seperate cracks with a total of about 55 – 60 lineal inches combined.  This project was completed 2 – 3 hours faster because I used the FCAW process instead of the SMAW process.

Advertisements

Leave a comment

No comments yet.

Comments RSS TrackBack Identifier URI

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s